Homewood Suites
JDC was contracted to perform all structural demolition and bulk removal/abatement of identified ACMs & PCBs for existing residential and commercial structures located at the future site of the planned HOMEWOOD SUITES HOTEL structure. Challenges associated with the demolition operations for this project included proximity to the MBTA Green Line, in which large portions of the demolition work could only be accomplished in accordance with MBTA shut-downs for 3 hours, per night; scheduling with the owners/tenants of the residential structure located at the east end of the site, which was less than 1’ from the existing 30’-high concrete structure being razed; coordinating police details for sidewalk and lane closures to facilitate demolition of south side of the commercial structure, which fronted Rte. 9, a major artery in/out of Boston.