180 Telfod Street
Client:
Dellbrook Construction
Status:
Completed
Value:
$100K - $500K
Location:
Brighton, MA
JDC was hired by Dellbrook Construction Company to demolition to perform the complete demolition of three existing buildings totally 30,000 SF. This work involved demolition of a three story concrete building was directly adjacent to an active car wash driveway and active Western Avenue in Allston, Massachusetts. JDC installed and coordinated the installation of all temporary protection prior to the demolition of buildings. Other scope of work including removal of above grade story tanks, utility cut and cap, and installation of all site erosion controls.